Building better asphalt trails:
Design and construction guidelines for asphalt trails
By Eric West, P.E.
What's
the best trail surface? This question has been debated for decades, and
the answer is still the same: it depends on intended use, the setting,
the budget, and available materials. Asphalt has been the material of
choice for trails of many kinds throughout America. This article
provides the technical data, based on wide experience, for building the
most durable and cost-effective asphalt trails.
The
selection of surface material for trails and paths is primarily based
on anticipated type and intensity of trail use, as well as terrain,
climate, design life, maintenance, cost, and availability. Soft surface
materials are low cost, but require substantial maintenance and are not
suitable for many of the recreational activities today's trails and
paths are used for. Hard surface materials, specifically concrete and
asphalt, provide years of service with low maintenance.
The following are
the key elements to consider in building quality asphalt trails:
| |
 |
proper
drainage |
| |
 |
proper
sub-grade
compaction |
| |
 |
adequate
pavement
thickness |
| |
 |
adequate
pavement
compaction |
DRAINAGE
Bike
paths and trails should be constructed to match the existing topography
as closely as possible, however, longitudinal slopes should not exceed
five percent and a cross slope of two percent is desirable to provide
adequate drainage away from the pavement surface. Proper drainage is
one of the most important factors affecting pavement performance.
Proper drainage entails efficient removal of excess water from the
trail. Surface water runoff should be handled using swales, ditches and
sheet flow. Catch basins, drain inlets, culverts and underground piping
may also be necessary. These structures should be located off of the
pavement structure.
MIX DESIGN FOR
HOT MIX ASPHALT
| |
|
Not
all hot mix asphalt is the same, and the type used for a highway may
not be the appropriate mix for a trail or bike path. Specific mixes are
designed for specific applications. |
| |
| |
|
The
hot mix asphalt specified for your project should provide adequate
strength and durability. The overall objective for the design of
asphalt paving mixtures is to determine a cost-effective blend of
aggregates and asphalt that yields a mix having: |
| |
| |
 |
sufficient
asphalt
to provide durability |
| |
 |
adequate
stability
to resist distortion and displacement |
| |
 |
sufficient
voids
to provide for expansion and contraction due to temperature
fluctuations |
| |
 |
sufficient
workability to allow proper field compaction to resist moisture damage
and minimize segregation |
| |
 |
proper
aggregate
texture and hardness to provide sufficient skid resistance |
| |
 |
Specifications
for trail and bike path hot mix asphalt should address the specific
application and use, and allow the use of locally available aggregate,
where its quality is adequate for the project. The gradation
specification should be consistent with local specifications. It is
recommended that a SX 1/2" nominal maximum size gradation, or meeting
the state Department of Transportation criteria, be specified. |
| |
| |
|
Bike
paths and trails are not subjected to heavy loading. Many of these
paths are also constructed in terrain difficult for large construction
equipment to access. Thus the hot mix asphalt should have a reasonably
high asphalt cement content. This "rich" mix will provide excellent
durability and allow for ease of placement and compaction. In addition,
high asphalt binder content mixes reduce segregation potential and
improve the surface texture of the mix for this type of application. |
PAVEMENT
THICKNESS
The
first step in analyzing pavement thickness is determining the loading
the pavement will be subjected to. Pavements need to be designed to
support wheel loads from vehicles that will have access to them. These
may include emergency, patrol, snow removal, maintenance and other
motor vehicles.
The
next step is to determine the load carrying characteristics of the
native soil. A soils investigation should be performed to determine the
sub-grade strength, load support capabilities, ground water conditions,
and swell potential of the native soils. The soil investigation should
be performed with test hole locations at appropriate intervals to
account for the varying soil conditions that may be encountered.
Pavement
thickness is dependent on the loading that will be applied to the
pavement, the asphalt mix design and the ability of the underlying soil
to support the loads. Full depth asphalt pavement is the overwhelming
choice to distribute loads to the sub-grade. However, depending on the
existing soil's ability to support the loads, an aggregate base course
and/or geo-textile may be used to improve the stability and/or load
carrying capability of the native soil.
The
geo-technical engineer performing the soils investigation should
recommend design thicknesses for the pavement based on the anticipated
loading conditions and the results of strength testing performed on the
native soils. As soil conditions vary across the site, recommended
design thickness may change. The standards for determining the
supporting capabilities of the native soil vary depending on location.
The
most common test performed is the R-value, American Association of
State Highway and Transportation Officials (AASHTO) designation T -190
and T-99, American Society for Testing and Materials (ASTM) designation
D 2844. This test provides a relative soil strength to be applied to
nomographs, or design equations, which include environmental and
loading criteria for determination of a required structural number for
the pavement. The required structural number must be achieved by an
adequate thickness of pavement. Each pavement layer is assigned a
strength coefficient based on the type of material used. A dense graded
hot mix asphalt is assigned a coefficient of between 0.34 and 0.44,
based on research done by AASHTO, and the properties of the mix.
In
an area with reasonably good soil (R-value > 20), occasional
maintenance vehicle use, and good drainage, a required structural
number of approximately 1.6 is determined from design nomographs. To
determine the necessary thickness of hot mix asphalt, divide this
structural number by the strength coefficient of the material. For a
typical hot mix asphalt, we will assume a strength coefficient of 0.40.
The calculation of 1.6/0.4 provides a recommended pavement section of 4
inches of hot mix asphalt.
The
above example is typical of the method used by geo-technical engineers
to provide recommended pavement sections. This example is based on
numerous assumptions and should not be used for actual construction.
Your geo-technical engineer or landscape architect will provide site
specific information for your project.
In
general, it is recommended a minimum 3" of hot mix asphalt be used for
bike paths and trails where loading from vehicles will be negligible.
As soil conditions deteriorate and loading increases, the pavement
thickness should be increased.
SUBGRADE
Prior
to construction, vegetation should be cleared and stumps and roots
removed along the trail for a minimum of five feet outside the edge of
the proposed pavement. This will allow construction equipment access
and help prevent roots and growth from eventually encroaching on the
path. If adequate access width cannot be provided, the contractor will
be forced to use less efficient equipment with increased costs.
The
asphalt should be placed on compacted sub-grade that extends a minimum
of two feet beyond the edge of pavement. The edge of pavement should be
feathered with native soil to avoid any sharp drops from the trail
edge. The sub-grade should be prepared by removing topsoil and unstable
soil, shaping to grade, scarifying the surface to a minimum depth of
six inches, moisture conditioning, and compacting. The sub-grade should
be compacted to a minimum of 95% of standard Proctor density, AASHTO T
99, and the moisture should be maintained within 3% of optimum. If
aggregate base course is used in the pavement section it should be
compacted to a minimum of 95% of modified Proctor density, AASHTO T
180, ASTM D 1557.
Depending
on the soil conditions, compaction and moisture criteria may vary.
Consult your landscape architect or geo-technical engineer for
site-specific information. After compaction a soil sterilant and/or
root inhibitor should be applied. Application should be carefully
controlled to the pavement area only. Typical shaping, grading and
compaction crews consist of a motor grader or blade, landscape tractor
with back box for grading, and a rubber tire roller for compaction.
Additional compaction equipment and access to water may be required.
Prior
to placement of the asphalt pavement it is recommended the sub-grade be
proof rolled to highlight areas of uncompacted or unstable soil. This
may be accomplished using a loaded single axle or tandem dump truck or
a loaded rubber tire loader. Soft or unstable areas should be
recompacted or removed and replaced with stable soil. It is also
important that all utility installations, including sprinkler systems,
be complete prior to paving.
PLACEMENT
Placement
of the hot mix asphalt should be accomplished with a self-propelled
paver, where possible. Where pavers cannot be used, a spreader box
attached to a dump truck may be used. Minimum paver width is generally
eight feet. For widths less than eight feet cutoff shoes may be placed
in the screed to reduce the width of paving. The screed controls mat
thickness and crown. Vibratory screeds are typical and provide a small
amount of compaction prior to rolling. In general, the uncompacted mat
should be 1/4" thicker than the final desired thickness to allow for
densification during rolling operations.
The
hot mix asphalt should be delivered to the paver at a temperature
adequate to allow proper compaction. This depends upon the type of
asphalt cement used, but generally ranges between 235 to 300 degrees
Fahrenheit. The contractor's ability to achieve compaction is dependent
on the mix temperature, pavement thickness, subgrade temperature,
ambient temperature and wind velocity.
COMPACTION and
JOINT CONSTRUCTION
Compaction
should be accomplished immediately after placement by the paver. Steel
wheel vibratory rollers are generally used for initial breakdown
rolling behind the paver, followed by a steel wheel finish roller.
Depending on the compactibility of the mix, a pneumatic tired roller
may also be used. Minimize their tendency to pick up fine aggregate
from the surface with proper tire temperature or the use of a release
agent. It is recommended the hot mix asphalt be compacted to 92%-96% of
the Theoretical Maximum Specific Gravity, AASHTO designation T 209,
ASTM designation D 2041.
Joint
construction should be carefully done to ensure a uniform mat.
Longitudinal joints, which occur where mats are laid side to side,
should be constructed with a vertical face or a step taper. The step
taper should have a 1.5" vertical face at the surface, tapered at a 3:1
slope from this point to the subgrade. Prior to placing the adjoining
mat the joint should be tack-coated. Asphalt placed against a
longitudinal joint should overlap the existing asphalt by 1".
Compacting longitudinal joints should be accomplished by rolling from
the hot side of the asphalt. The steel wheel roller is placed with the
majority of the drum on the hot, newly placed asphalt, with
approximately 6" of the drum extending over the cold asphalt.
Transverse
joints occur at any point the paver ends work and then resumes at a
subsequent time. The end of the paving mat should be cut off vertically
to allow the full lift thickness to be placed against it. Lumber is
used as a bulkhead, paving over the lumber and leaving a taper that is
removed along with the bulkhead prior to resumption of paving. Another
method is to form a papered transverse joint where heavy wrapping paper
is placed along the entire face of the vertical edge of the pavement.
The paper extends approximately three to four feet onto the subgrade.
The paver resumes paving over the paper to form a taper. Prior to
resumption of paving, the paper and material on top of it is removed
forming a vertical edge.
When
paving resumes the vertical edge is tack-coated, heated and the paver
backed over the existing asphalt with the screed resting on the
previously placed mat. The shims should have a height equal to the
expected compacted thickness, i.e. 1/4" per inch of material. Mix is
delivered to the paver and the paver starts forward slowly. Excess mix
left by the paver is bumped back to the joint location and/or removed.
The joint is then rolled transversely from the cold side beginning with
the roller approximately six inches on the newly placed mat and
continuing across in six to twelve inch increments. Timbers should be
placed along the outside edges of the mat to support the roller and
minimize distortion of the outside edges.
Composite
sections, consisting of asphalt pavement overlying aggregate base
course, have an advantage in the ease of grading the base course to the
proper level for placement of the asphalt pavement. If base course is
used it should be a minus 1-1/2" and minus 3/4" aggregate size. The
strength coefficient of base course ranges from 0.12 to 0.14, depending
on the R-value of the material. Based on this strength coefficient, 3"
of base course are equivalent to the strength of 1" of asphalt
pavement. However, when using aggregate base course, the asphalt
pavement thickness should be maintained at 3" and should never be less
than 2". The minimum thickness of the aggregate base course should be
6" for an asphalt trail, or thicker for poorer quality sub-grade
material.
The
subgrade should be stripped of vegetation, shaped to grade, and
compacted at the proper moisture content prior to placement of the
pavement structure. In general, compact the sub-grade to a minimum of
95% of the maximum density as determined by AASHTO T 99, Standard
Proctor and maintain moisture content to within 3% of optimum. Again,
your geo-technical engineer or landscape architect should provide
guidelines for proper compaction of the existing soil.
A more detailed
report,
is available on the American Trails website: www.AmericanTrails.org
(click on "Resources & Library" and click on "Trail Construction").
Thanks to the Colorado Asphalt Pavement Association for
allowing use of this text.
(Excerpted
from the Colorado Asphalt Pavement Association via Asphalt
Trails website.)
|